[2021] PRINCE2-Foundation Exam Dumps, Test Engine Practice Test Questions
Pass PRINCE2-Foundation exam [Dec 18, 2021] Updated 310 Questions
For more info visit:
The benefit in Obtaining the PR2F Exam Certification
- Becoming Exin Project Management means one thing you are worth more to the company and therefore more to yourself in the form of an upgraded pay package. On average, an Exin Project Management member of staff is estimated to be worth 30% more to a company than their uncertified professionals.
- After completion of Exin Project Management Candidates receive official confirmation from Exin that you are now fully certified in their chosen field. This can be now added to their CV, cover letters and job applications.
- When Candidates applying for a job or looking to promotion in their current position, an Exin Project Management Certification in the field in which Candidates are applying will put you at the top of the list and make them a desirable candidate for employers.
- Organization owners invest a lot in their employees when it comes to their training with the goal of making them quicker, more efficient, and more knowledgeable about their role. Certified Professional will reduce the time he spends on tasks, meaning he can get more done this could help reduce company downtime when repairing faults on a system or fixing hardware problems.
- Candidates will get in-depth knowledge by completing the courses along with the access to revision materials for 6 months upon completion means they will have a wider skill set when it comes to the various technologies and systems than an uncertified professional. Certified Professional in this particular skill set is 74% more efficient when it comes to completing their tasks in a timely well-executed manner.
NEW QUESTION 71
What should the benefits management approach define?
- A. How the project has progressed against its plans
- B. The suitability of the project management team structure
- C. What actions will be taken to ensure the project's outcomes are achieved
- D. What will be used to record the effectiveness of the project's approaches
Answer: A
Explanation:
Section: Volume B
NEW QUESTION 72
Which is NOT a purpose of a Benefits Review Plan?
- A. Define the period over which the cost-benefit analysis will be based
- B. Describe how to measure the performance of the project's products in operational use
- C. Define the scope, timing and ownership of the benefit reviews required
- D. Describe how to measure and confirm any benefits that are to be realised after the project is closed
Answer: A
Explanation:
Section: Volume A
NEW QUESTION 73
What product forms the contract' between the Project Board and the Project Manager?
- A. Project Initiation Documentation
- B. Project mandate
- C. Project Plan
- D. Project Brief
Answer: A
NEW QUESTION 74
Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?
- A. Project Initiation Documentation
- B. Project mandate
- C. Benefits Review Plan
- D. Project Brief
Answer: A
NEW QUESTION 75
Which should be provided by corporate or programme management before the Starting up a Project process commences?
- A. A Project Brief
- B. The Project Initiation Documentation
- C. Sufficient information to identify the prospective Executive
- D. Authority to initiate a project
Answer: C
Explanation:
Section: Volume B
NEW QUESTION 76
Which of the following statements about quality assurance and Project Assurance is true?
- A. Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization
- B. Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board
- C. Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board
- D. Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager
Answer: A
NEW QUESTION 77
Which of the following describes a use of a Configuration Item Record?
- A. To record the history of a product
- B. To record how changes to a product will be controlled
- C. To provide information on theapproval procedure for the Work Package
- D. To pass responsibility for the delivery of a product to a Team Manager
Answer: A
NEW QUESTION 78
According to the 'continued business justification' principle, what must project benefits be aligned to?
- A. The business objectives
- B. The technology available
- C. The direction of the project board
- D. Regular deliveries throughout the project
Answer: A
Explanation:
Explanation/Reference:
Reference https://www.whatisprince2.net/prince2-principle-continued-business-justification.php
NEW QUESTION 79
Which is an objective of the Managing Product Delivery process?
- A. Report progress to the Project Board
- B. Sign-off completed Work Packages
- C. Ensure the Business Case is kept under review
- D. Ensure that work on products is authorized and agreed with the team
Answer: D
NEW QUESTION 80
Which level of management sets the project level tolerances?
- A. Project manager
- B. Project board
- C. Corporate, programme management or the customer
- D. Team manager
Answer: A
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Manage_by_exception
NEW QUESTION 81
Which is one of the six aspects of project performance that needs to be managed?
- A. Progress
- B. Risk
- C. Security
- D. Change
Answer: B
NEW QUESTION 82
Which is a minimum requirement for applying the quality theme?
- A. The quality review technique must be used when reviewing products
- B. Appraisal methods of quality control must be carried out on products
- C. The quality management approach must align with corporate standards
- D. A record must be kept of all the quality management activities that are planned
Answer: D
Explanation:
Section: Volume B
Explanation/Reference:
NEW QUESTION 83
Which of the following statements about stakeholders are true?
1.Someone who thinks they will be affected by a project is a stakeholder on that project
2.Stakeholders may be internal or external to the corporate organization
- A. Both 1 and 2 are true
- B. Neither 1 or 2 are true
- C. Only 2 is true
- D. Only 1 is true
Answer: A
NEW QUESTION 84
Which document should record the agreed amount of risk budget for a project?
- A. Risk Register
- B. Project Plan
- C. Risk Management Strategy
- D. Project Brief
Answer: B
NEW QUESTION 85
Which process is used to define how baselines will be established and controlled?
- A. Starting up a project
- B. Directing a project
- C. Controlling a stage
- D. Initiating a project
Answer: A
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Quality
NEW QUESTION 86
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
- A. Risk Register
- B. Off-specifications
- C. Follow-on action recommendations
- D. Issue Register
Answer: C
NEW QUESTION 87
Which is NOT one of the PRINCE2 integrated elements?
- A. The themes
- B. Tailoring PRINCE2 to the project environment
- C. The products
- D. The processes
Answer: C
Explanation:
Section: Volume A
NEW QUESTION 88
......
PRINCE2 Foundation PR2F Exam
PRINCE2 Foundation PR2F Exam which is related to Exin PRINCE2 Foundation and credits toward Exin Project Management Certification. This exam focuses on the characteristics and context of a project and the benefits of adopting PRINCE2 the purpose of the PRINCE2 roles management, products, and themes, objectives and context of the PRINCE2 to process. It also deals with the ability to provide a structured universally acceptable project management method that covers the PRINCE2 principles, themes and processes required to successfully deliver the projects within time, cost and quality constraints.
PRINCE2 PRINCE2-Foundation Real 2021 Braindumps Mock Exam Dumps: https://vcepractice.pass4guide.com/PRINCE2-Foundation-dumps-questions.html